New hotspots driving cost hikes in key data centre markets

- Advertisment -

Latest report  highlights thriving Data Centre market in South Africa and spread of activity across Sub-Saharan Africa

Teraco Riverfields HyperScale Data Centre under construction in 2017

“Data continues to be one of the most valuable commodities. As deals get bigger and more profitable, investment in both established hot spots and emerging markets heat up – putting pressure on cost and resources according the latest report from Turner & Townsend

The Data Centre Cost Index 2019 highlights the intensification of investment in leading locations in the global data centre network as a trigger for escalating costs.  Globally, over 40 percent of markets surveyed are showing ‘hot’ construction conditions – where competition for supply chain resources is putting pressure on budgets.

The research analyses input costs, including labour and materials, across 32 key markets, alongside industry sentiment and insight from data centre professionals.

Hotspots in Africa

The 2019 report points to the rise of new hotspots across the globe as technological investment in emerging economies takes hold.  On the African continent, in Nairobi, Kenya, average build costs stand at $6.5 US per watt on the back of investment required to meet the government’s focus on digitisation of the economy and in response to the arrival of tech giants.

South Africa is highlighted as another emerging market on the continent. With total GDP exceeding US$315bn, internet literacy now stands at 55% amongst its 50 million citizens. South Africa is ranked 23rd globally on Cloud scene based on data centre density.

Dan Ayley, global head of hi-tech and manufacturing for Turner & Townsend

Dan Ayley, global head of hi-tech and manufacturing for Turner & Townsend, says: “Nairobi has risen three places from last year’s table to take position 20, indicating the spread of market activity across Sub-Saharan Africa. It’s still more expensive to build a data centre in Nairobi than Johannesburg, which remains in cost spot 25 with average build costs of at $6.2 US per watt.”

A thriving industry in South Africa

With several submarine cables interconnecting South Africa to Asia and Europe, Johannesburg has up to 52 internet users per 100 people, and the connectivity ecosystem is made up of 60 colocation data centres, 319 cloud service providers and six network fabrics.

According to the report the data centre construction markets in both Johannesburg and Cape Town are hot with key projects coming to fruition and hyperscale investments increasing, with South Africa being seen as a steppingstone into the rest of the African continent.

“South Africa’s data centre industry is thriving, with Johannesburg its single largest market by some margin – twice the size of Cape Town. Last year (2019) saw an increase in market size in both Cape Town and Johannesburg,” adds Ayley.

The global picture

Global demand for new space for data centres looks set to continue into 2020, with just nine per cent of respondents to the research believing that demands have been met in their markets in the last year – down from 12 per cent in 2018.  Seventy percent of those surveyed highlighted the impact of data sovereignty and data protection acts – including those being brought in by the EU, Switzerland and Kenya – as a major catalyst for demand.

The most significant limiter on growth over the next five years is seen as availability of power, especially in the context of pressure on the industry to decarbonise. In Turner & Townsend’s survey, the industry is split 50:50 on whether technological advances with solid state batteries alongside green energy sources can render traditional fossil fuel generators obsolete.

Pressing challenges

“Although our report points to certainty in delivery as the key issue for the sector across global markets, sustainability is one of the most pressing challenges coming down the track. With power density requirements for data centres increasing by as much as 50 per cent year on year, it demonstrates that steps towards decarbonisation need to be a priority for how hubs are conceived, built and operated across their lifecycle.”

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Latest articles

Download the February Edition

The first edition of the “new” EngineerIT is now available for download. Explore these and many other articles including: SANSA App calculates best HF communication channel The...

New device offers more security for GNSS applications

GNSS (Global Navigation Satellite System) is a satellite system that is used to pinpoint the geographic location of a user's receiver anywhere in the...

The Curse of the Password – What must I do? I’ve been hacked

By cyber security expert and J2 Software CEO John Mc Loughlin With all the hype around cyber-attacks and every single cyber security enterprise talking about...

Huawei launches 5G Training at Walter Sisulu University

As part of a partnership to equip South African students to succeed in the Fourth Industrial Revolution (4IR), Huawei and the Department of Communications...

New POPI Act regulations tough on disposing of old computer gear. Huge fines!

Wale Arewa, CEO ExperienDisposing of old computer equipment used to be a mindless process, but those methods of the past are no longer an...

What will feature in the March EngineerIT?

The main feature in the March edition will be on ICT. ICT is pervasive and has found it way into every sector of industry,...
- Advertisement -

Once-off decisions when moving to the cloud are dangerous

According to Andre Schwan at T-Systems South Africa, many companies embark on their cloud journey, only to further down the line regret early decisions...

Social Entrepreneurship FIX Scholarship

The Fix Scholarship is a non-profit organisation that offers female social entrepreneurs, who pursue entrepreneurial solutions for urgent social development challenges, the opportunity to complete the...

Earth’s magnetic field is humming today

A G1-class geomagnetic storm is underway today (19 February 2020) as the Earth enters a minor stream of solar wind. Even before the solar wind...

Do you remember dialling up to the Internet?

That is what it was like on 16 January when a simultaneous dual submarine cable break occurred in the early hours of that disastrous...

February edition out this week

The February edition of the “new” EngineerIT under the Now Media banner will be published later this week. We have converted at least 900 addresses...